diff --git a/docs/technical-documentation/project/workbreakdown-faas/faas-wbs.md b/docs/technical-documentation/project/workbreakdown-faas/faas-wbs.md index 4e34a9c..42c64a0 100644 --- a/docs/technical-documentation/project/workbreakdown-faas/faas-wbs.md +++ b/docs/technical-documentation/project/workbreakdown-faas/faas-wbs.md @@ -2,6 +2,14 @@ Below is a work breakdown structure for the "FaaS" milestone. +## Executive Summary + +* the milstone `FaaS Product ready` is on 06/30/25 +* there will be some additional work which goes into milestone `FaaS Product finalized` until mid of July +* Work is illustrated + * as parallel tasks which need to be dispatched in their real order on a daily basis + * or they have a dependency, then they follow the preceeding task + ```mermaid gantt title EDP Milestone 'FaaS' Work Breakdown Structure @@ -10,20 +18,21 @@ gantt Begin OTC IaC :milestone, m1, 2025-05-02, 0m Begin observabiliy :milestone, m2, 2025-05-20, 0m Foundry Cluster ready :milestone, m3, 2025-06-10, 1d - FaaS Product ready :milestone, m4, 2025-07-16, 1d + FaaS Product ready :milestone, m4, 2025-06-30, 1d + FaaS Product finalized :milestone, m5, 2025-07-16, 1d section Forgejo as a Service Create Kubernetes IaC Stack :done, iac, after m1, until m3 Observability :done, observability, after m2, until m3 - Runner Concept and implemenatation :runner, after m3, 15d - Secure Prod Env (WAF) :secprod, after test-ressource, 5d + Runner Concept and implemenatation :runner, after m4, 10d + Secure Prod Env (WAF) :secprod, after test-ha, 5d section Test FaaS Service - Test HA of central service :test-ha, after m3, 12d + Test HA of central service :test-ha, after m3, 7d Test HA of observability :test-obs, after m3, 7d - Deployment, accounting and billing concept for friendly user service consumption :deployment-concept, after m3, 12d - Test secure Deployment/Destroyment :test-ressource, after deployment-concept, 5d - test day-2 operations :day-2, after test-ressource test-ha test-obs, 12d + Deployment, accounting and billing concept for friendly user service consumption :deployment-concept, after m3, 7d + Test secure Deployment/Destroyment :test-ressource, after deployment-concept test-ha test-obs, 5d + test day-2 operations :day-2, after test-ressource, 7d Test Customer Onboarding :onboarding, after deployment-concept, 5d section Check and document specified Product capabilities @@ -35,8 +44,8 @@ gantt Registry :reg, after vcs, 4d Container Registry :ocireg, after reg, 4d Code review :cr, after vcs, 4d - CI/CD :cicd, after runner, 8d - Security Scanning :sec, after runner, 12d + CI/CD :cicd, after m3, 8d + Security Scanning :sec, after m3, 12d section Forgejo as Portal Frontend T Design Features :design, 2025-05-28, 23d @@ -46,7 +55,11 @@ gantt section Deployment Production Deployment :proddeploy, after secprod day-2, 6d + section CFor Migration + Migrate EDP Cfor to OTC :migrate-cfor, after m3, 5d + ``` +## appendix ![alt text](wps-annotations.jpg) \ No newline at end of file