# Work Breakdown Structure: Milestone "FaaS" Below is a work breakdown structure for the "FaaS" milestone. ## Executive Summary * the milstone `FaaS Product ready` is on 06/30/25 * there will be some additional work which goes into milestone `FaaS Product finalized` until mid of July * Work is illustrated * as parallel tasks which need to be dispatched in their real order on a daily basis * or they have a dependency, then they follow the preceeding task ```mermaid gantt title EDP Milestone 'FaaS' Work Breakdown Structure dateFormat YYYY-MM-DD axisFormat %d.%m. Begin OTC IaC :milestone, m1, 2025-05-02, 0m Begin observabiliy :milestone, m2, 2025-05-20, 0m Foundry Cluster ready :milestone, m3, 2025-06-10, 1d FaaS Product ready :milestone, m4, 2025-06-30, 1d FaaS Product finalized :milestone, m5, 2025-07-16, 1d section Forgejo as a Service Create Kubernetes IaC Stack :done, iac, after m1, until m3 Observability :done, observability, after m2, until m3 Runner Concept and implemenatation :runner, after m4, 10d Secure Prod Env (WAF) :secprod, after test-ha, 5d section Test FaaS Service Test HA of central service :test-ha, after m3, 7d Test HA of observability :test-obs, after m3, 7d Deployment, accounting and billing concept for friendly user service consumption :deployment-concept, after m3, 7d Test secure Deployment/Destroyment :test-ressource, after deployment-concept test-ha test-obs, 5d test day-2 operations :day-2, after test-ressource, 7d Test Customer Onboarding :onboarding, after deployment-concept, 5d section Check and document specified Product capabilities Create Template Apps :apps, after m3, 15d Documentation :doc, after m3, 4d Project Mgmt :pm, after m3, 4d VCS :vcs, after pm, 4d Branch Protection :vcsbranch, after vcs, 4d Registry :reg, after vcs, 4d Container Registry :ocireg, after reg, 4d Code review :cr, after vcs, 4d CI/CD :cicd, after m3, 8d Security Scanning :sec, after m3, 12d section Forgejo as Portal Frontend T Design Features :design, 2025-05-28, 23d Portal Frontend Architecture :pfarch, after m3, 15d PF Dev Flow (inc.Forgejo Pipelines) : pfdev, after runner deployment-concept pfarch, 8d section Deployment Production Deployment :proddeploy, after secprod day-2, 6d section CFor Migration Migrate EDP Cfor to OTC :migrate-cfor, after m3, 5d ``` ## appendix ![alt text](wps-annotations.jpg)