Below is a work breakdown structure for the "FaaS" milestone.
## Executive Summary
* the milstone `FaaS Product ready` is on 06/30/25
* there will be some additional work which goes into milestone `FaaS Product finalized` until mid of July
* Work is illustrated
* as parallel tasks which need to be dispatched in their real order on a daily basis
* or they have a dependency, then they follow the preceeding task
```mermaid
gantt
title EDP Milestone 'FaaS' Work Breakdown Structure
@ -10,20 +18,21 @@ gantt
Begin OTC IaC :milestone, m1, 2025-05-02, 0m
Begin observabiliy :milestone, m2, 2025-05-20, 0m
Foundry Cluster ready :milestone, m3, 2025-06-10, 1d
FaaS Product ready :milestone, m4, 2025-07-16, 1d
FaaS Product ready :milestone, m4, 2025-06-30, 1d
FaaS Product finalized :milestone, m5, 2025-07-16, 1d
section Forgejo as a Service
Create Kubernetes IaC Stack :done, iac, after m1, until m3
Observability :done, observability, after m2, until m3
Runner Concept and implemenatation :runner, after m3, 15d
Secure Prod Env (WAF) :secprod, after test-ressource, 5d
Runner Concept and implemenatation :runner, after m4, 10d
Secure Prod Env (WAF) :secprod, after test-ha, 5d
section Test FaaS Service
Test HA of central service :test-ha, after m3, 12d
Test HA of central service :test-ha, after m3, 7d
Test HA of observability :test-obs, after m3, 7d
Deployment, accounting and billing concept for friendly user service consumption :deployment-concept, after m3, 12d
Test secure Deployment/Destroyment :test-ressource, after deployment-concept, 5d
test day-2 operations :day-2, after test-ressource test-ha test-obs, 12d
Deployment, accounting and billing concept for friendly user service consumption :deployment-concept, after m3, 7d
Test secure Deployment/Destroyment :test-ressource, after deployment-concept test-ha test-obs, 5d
test day-2 operations :day-2, after test-ressource, 7d
Test Customer Onboarding :onboarding, after deployment-concept, 5d
section Check and document specified Product capabilities
@ -35,8 +44,8 @@ gantt
Registry :reg, after vcs, 4d
Container Registry :ocireg, after reg, 4d
Code review :cr, after vcs, 4d
CI/CD :cicd, after runner, 8d
Security Scanning :sec, after runner, 12d
CI/CD :cicd, after m3, 8d
Security Scanning :sec, after m3, 12d
section Forgejo as Portal Frontend
T Design Features :design, 2025-05-28, 23d
@ -46,7 +55,11 @@ gantt
section Deployment
Production Deployment :proddeploy, after secprod day-2, 6d
section CFor Migration
Migrate EDP Cfor to OTC :migrate-cfor, after m3, 5d
```
## appendix
![alt text](wps-annotations.jpg)